Main image of article Inherited a Troubled Tech Project? Make Your First Promise One You Can Keep

You’ve just inherited a project that’s already late, and the project sponsor wants a launch date for the next board update. The status report looks reassuring. Then you start asking what’s been tested, which systems still depend on the old one, and what the team means by “done.” The answers can change the work you’re being asked to put a date on.

The tech leaders who’ve had to make that first promise describe commitments they could keep while they figured out what it would take to ship. One offered a launch window he’d narrow after vendor testing. Another worked with engineers to define a smaller piece users could actually use. For the leader inheriting a stalled ERP rollout, the first commitment was a timetable for giving the sponsor enough evidence to decide whether to salvage the rollout at all.

Put a date on the assessment

When Chris McGlasson, fractional CIO and founder of ClearStack Advisory, took over a cloud ERP rollout, the client had already tried to go live three times. McGlasson says the documentation didn’t match what had been built, the status reports couldn’t be trusted, and employees were running the business in Excel. The sponsor wanted another go-live date.

“I committed to dates for answers instead of a date for go-live,” McGlasson says. He committed to halting unnecessary vendor spending within 48 hours, producing a basic roadmap within 21 days and providing a phased budget and timeline within 30 days. In between, the sponsor would get a one-page weekly update on issues and spending.

Each checkpoint served a purpose. The proposed pause was meant to limit vendor spending during the review. The roadmap would give leadership a basis for deciding whether to salvage the rollout or take another route. The budget and timeline would show what carrying out that decision would take. To make the first commitment stick, McGlasson needed the sponsor to back the pause with both the vendor and the internal team.

That backing mattered as soon as the assessment began. McGlasson was reviewing both the vendor agreement and what the vendor had actually built. With the records out of sync and staff working in spreadsheets, the existing plan gave him little basis for judging which work was worth paying for.

“The rollout kept costing money every week it sat there, and I could not do an honest assessment while the meter was running on work nobody could show me was needed,” McGlasson says.

If you inherit a project with active vendor work, bring that decision into the first sponsor conversation. Identify which spending you’re proposing to pause and who has the authority to tell the vendor. Put any work the team needs to continue on the table at the same time.

Find out what the status report measures

Riken Shah, founder and CEO of healthcare software company OSP, was nine days into taking over a delayed health insurer’s member portal when he was asked for a date for a board update. The test report showed 85 percent passing, he says, but the team had manually marked some tests as passed because the eligibility vendor’s sandbox behaved differently from production.

“Nobody hid it. The team had worked around a real constraint. The project went from late with open defects to an unvalidated integration at its center,” Shah says.

Shah asked for a scope freeze, direct access to the vendor’s technical lead and two senior engineers for eight weeks.

Shah’s initial commitment was a two-week assessment, a written plan and weekly updates showing what the team had verified against production-like data. His launch window stretched from late September to mid-November. He promised to narrow the window after end-to-end vendor testing in week three. By giving the sponsor both a window and the test that would inform the next estimate, he made the uncertainty specific enough to discuss at the next review.

“I also asked the sponsor to let me revisit the date twice without it counting as a failure, which let us report bad news early,” Shah says.

That’s a term you can negotiate before a forecast goes to the board. Agree on which checkpoint could change the range and how you’ll explain a change. The sponsor can then tell the board what the range depends on and when to expect an update.

Trace where the data actually goes

For Timur Rakhmatullin, a senior software engineer at Softline Solutions, the surprise on an earlier project at game developer MyTona came from tracing where the data actually went. Some jobs were still writing to a MySQL instance that should have been decommissioned. Reconciling the data became part of the migration, and Rakhmatullin says his estimate roughly doubled. His interim commitments included a decision log that recorded who made each technical choice and why.

The request that started the MyTona takeover was whether the migration could reach production by the end of the quarter, five weeks away. Rakhmatullin committed to a working staging environment within two weeks so stakeholders could see what was working while he evaluated the production schedule.

“I had opened exactly one config file, saw it referenced four services I did not know existed, and closed my laptop. I told him I could promise him a written assessment in ten days,” Rakhmatullin says.

The decision log also recorded the alternative the team had considered. That gave engineers a way to reconstruct the reasoning behind an early decision if the next discovery called it into question.

Rakhmatullin says he learned to speak to engineers before settling on an explanation for the sponsor. On a later takeover, he spent his first three days in one-on-ones with people who had worked on the system. Those conversations surfaced race conditions that were causing duplicate charges, a problem that hadn’t been escalated.

Define what the team can deliver or retire

Stephanie Weber, co-founder of Understory Collaborative, inherited a reporting project in a prior product role. Stakeholders kept adding scope while engineers quietly adjusted user stories in progress. She brought the team together to agree on what "done" looked like, then broke the work into user-journey slices. Each slice was a piece of a feature the team could estimate that gave users a new capability.

“When it’s completed, the user can do something they couldn’t do before and they see value in it,” Weber says. The test for a useful first milestone is whether you can name that new capability and show it working.

Some recoveries need a different kind of commitment. Adam Wachtel, CTO at Click Boarding, inherited a platform with client-specific builds and newer features that had never fully replaced older versions. He committed to a sequence for stabilizing the platform and building the team. That required leadership backing to move clients onto standard tools so the old infrastructure could be shut down.

Wachtel says he initially underestimated how much work each fix would uncover. The team was thin, and it needed senior architects and people in product, QA and DevOps to maintain the platform and develop new features.

Retiring the old systems also depended on moving users onto the standard tools first. Each customer still using a custom build represented work the team had to account for in the transition.

“Thankfully, our leaders understood what was needed and the system got faster and cheaper to maintain so the team could spend its time building instead of firefighting,” Wachtel says.

He says retiring the old technical debt took more than two years. If your recovery depends on retiring a system, identify the customers still using it and who can approve moving them. That gives the team a way to explain the order of work and show which steps are complete while the final date remains uncertain.

Before you leave the first sponsor meeting, agree on what you’ll bring back, when you’ll bring it back, and who can act on it. If validating the schedule requires a vendor’s help, get that access on the table. If the plan depends on cutting scope or retiring a system, establish who can make that call. A useful first promise gives the team work it can start today and gives the sponsor a decision they can make when the evidence comes in.